To be constructed between Mecca-Jeddah-King Abdullah Economic City and Medina in Saudi Arabia, Medina station project, among the stations consisting of the second parcel of the first step of 450 km lenght of Haramain High Speed Rail project, was built by Yapi Merkezi.
INTEK Formwork systems, used in the project, and quantities are as follows:
SLAB FORMWORKS
HD 150 tableform system – A=7.205 m2
FOUNDATION FORMWORKS
Panex system – A=638 m2
WALL FORMWORKS
Panemax system – A=335 m2
Inteva system – A=2.807 m2
COLUMN FORMWORKS
SCS PNM system – A=239 m2 (15 sets)
Inteva system – A=284 m2 (17 sets)
The consultancy firms in Saudi Arabia acting on behalf of employing firms scrutinise all the companies serving the project and all the materials to be used in the construction in detail and if there is no inconvenience, they approve them. In order to obtain this approval, it was realized a very detailed presentation involving formwork application projects and static calculations on formworks and then necessary approvals were received by the consultant, DAR Engineering. Below, you will have a part of column formwork calculation in 104-page of display book.